Data
Government contracts tracker
Contract awards published by the National Procurement and Tender Administration (NPTA). 10,872 awards on record, updated hourly.
Awards in 2026
888
Value in G$ (2026)
G$45.5 billion
plus 44 awards in US$
Largest buyers in 2026 (G$)
- Guyana Water Inc.G$5.79 billion
- Ministry of EducationG$4.85 billion
- Ministry of Public Utilities & AviationG$4.56 billion
- Ministry of Public WorksG$4.33 billion
- Ministry of HealthG$3.75 billion
Largest contractors in 2026 (G$)
- Lena Engenharia E. Construcoes , Proyectos E. Innovacion Cinco, Excel Guyana Inc, Latitude Geospatial Consultancy Inc (J.V)G$3.62 billion
- Jiangsu Gaia Enviromntal Technology Co. LtdG$3.48 billion
- Dax Contracting ServicesG$1.30 billion
- Fix-It DepotG$1.24 billion
- BK International Inc.G$1.03 billion
10,872 awards
| Awarded | Buyer | Contract | Awarded to | Amount | Bids |
|---|---|---|---|---|---|
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Roopan Ramotar Investment L23 | G$83.0 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Quantas Construction Services and Supplies Incorporated L22 | G$79.4 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Applied Services L21 | G$80.6 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Well Built Construction Services L20 | G$117 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Crown Road & Drainage Contractors L19 | G$118 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Box Construction and Supplies L18 | G$119 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | AJM Enterprise L17 | G$113 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Romell Jagroop General Construction Service L16 | G$118 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Compass Industrial Services L15 | G$118 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Kingston Strategic Inc. L14 | G$101 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Keystone Industries L13 | G$82.4 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Associate Investments L12 | G$85.5 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | HRS Investment and Logistics Inc. L11 | G$76.8 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Star Imports & Trading L10 | G$67.0 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Abrams General Contracting Services Inc. L9 | G$76.4 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Epcot Enterprise Inc. L8 | G$103 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Fyuse Hoosain Construction Inc L7 | G$103 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | D. Sawh Mechanical Workshop L6 | G$93.0 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | G.S.K Excavation Services Inc. L5 | G$93.9 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | KGM Construction & Supply Inc. L4 | G$93.0 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | M.K Hoosien Contracting L3 | G$94.6 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | Buddy's Construction L2 | G$92.2 million | 34 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Construction of Flood relief and River Defence Embankments in Region 5 489/2025/21 · NCB | K&S Peetum Construction L1 | G$91.2 million | 34 |
| 31 Dec 2025 | Ministry of Home Affairs | Furnishing of CANU Headquarters and Modification to Storage Bond and Admin Building 694/2025/51 · NCB | LF Global | G$125 million | 4 |
| 31 Dec 2025 | Ministry of Health | Rehabilitation and Upgrading of Electrical System at the Mahdia District hospital 318/2025/47 · NCB | H2 Asset (Guyana) Inc & Cummings Electrical & Co Ltd Joint Venture | G$340 million | 3 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Supply of Fix Drainage Pumps tot the NDIA 550/2025/21 · NCB | D.Sawh Mechanical Workshop L7 | G$68.8 million | 2 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Supply of Fix Drainage Pumps tot the NDIA 550/2025/21 · NCB | D.Sawh Mechanical Workshop L6 | G$68.8 million | 2 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Supply of Fix Drainage Pumps tot the NDIA 550/2025/21 · NCB | D.Sawh Mechanical Workshop L5 | G$406 million | 2 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Supply of Fix Drainage Pumps tot the NDIA 550/2025/21 · NCB | D.Sawh Mechanical Workshop L4 | G$200 million | 2 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Supply of Fix Drainage Pumps tot the NDIA 550/2025/21 · NCB | D.Sawh Mechanical Workshop L3 | G$316 million | 2 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Supply of Fix Drainage Pumps tot the NDIA 550/2025/21 · NCB | D.Sawh Mechanical Workshop L2 | G$255 million | 2 |
| 31 Dec 2025 | MoA - National Drainage & Irrigation Authority- | Supply of Fix Drainage Pumps tot the NDIA 550/2025/21 · NCB | D.Sawh Mechanical Workshop L1 | G$255 million | 2 |
| 31 Dec 2025 | Ministry of Culture, Youth and Sport | Design and Build Proposals for International Cricket Field at Cricket Academy Good Hope 403/2025/44 · NCB | Superior Group Inc. | G$327 million | 1 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Janitorial and Cleaning Supplies 437/2025/51 · NCB | Imperial Trading | G$120,000 | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Janitorial and Cleaning Supplies 437/2025/51 · NCB | Mike's Pharmacy | G$816,500 | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Janitorial and Cleaning Supplies 437/2025/51 · NCB | Reliance Services | G$120,000 | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Janitorial and Cleaning Supplies 437/2025/51 · NCB | United Trading & Business Services | G$1.3 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Janitorial and Cleaning Supplies 437/2025/51 · NCB | I&S Sanksr's importers & Distributors | G$684,000 | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Janitorial and Cleaning Supplies 437/2025/51 · NCB | Paradise Food Product | G$7.4 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Janitorial and Cleaning Supplies 437/2025/51 · NCB | Guybiz Establishment | G$2.8 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Janitorial and Cleaning Supplies 437/2025/51 · NCB | MS Trading | G$1.7 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Janitorial and Cleaning Supplies 437/2025/51 · NCB | Memorex Enterprise | G$2.4 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Janitorial and Cleaning Supplies 437/2025/51 · NCB | P. Ramroop & Sons | G$6.2 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Janitorial and Cleaning Supplies 437/2025/51 · NCB | Regal Stationery and Computer Centre | G$1.1 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Construction of Farm at Mazaruni Prison Lots 1-5 856/2025/51 · NCB | Gryphon Engineering Inc. | G$190 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Construction of Farm at Mazaruni Prison Lots 1-5 856/2025/51 · NCB | Gopie Invetsemnt Inc. | G$70.5 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Construction of Farm at Mazaruni Prison Lots 1-5 856/2025/51 · NCB | Emeralds General Contracting and Distributors | G$87.2 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Construction of Farm at Mazaruni Prison Lots 1-5 856/2025/51 · NCB | Tripple P Construction and General | G$72.0 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Construction of Farm at Mazaruni Prison Lots 1-5 856/2025/51 · NCB | Andrect Engineering & Construction | G$41.4 million | 26 |
| 31 Dec 2025 | Ministry of Home Affairs | Procurement of Medical Supplies, Guyana Prison Service 129/2025/51 · NCB | New GPC Inc. | G$45.1 million | 3 |
Source: NPTA, Tenders Awarded. Shown as NPTA publishes them; amounts and dates are not corrected. Totals count G$ awards only. NCB: national competitive bidding; ICB: international competitive bidding.