Department of Public Information: GPL work due by 30 November
The Department of Public Information said GPL expects to finish one stretch by 30 November, but the Good Hope-to-Mahaica section needs several more months.

The Department of Public Information said GPL has indicated it will finish its electricity work on the stretch from Goedverwagting to Good Hope by 30 November. The department published the statement on 11 November 2026.
It is a US$192 million contract to widen the road, run by China Railway First Group. The contract runs from Sheriff Street to Orange Nassau, and subcontractors move GPL's lines.
The Department of Public Information said some electricity poles still stand in the widened road. It said contractors laid a first layer of asphalt around the poles. The aim is to cut dust for nearby households while the poles await removal.
Guyana Times reported that in October 2025 President Ali said nearly every lane on the Mahaica to Good Hope stretch now had a road surface. Only the sections where utilities were in the way were left. The paper said he told GPL to speed up the move.
Guyana Times reported that GPL is also building a new route for 69kV transmission lines, which carry electricity. The route starts at the Goedverwagting Substation and heads towards Mahaicony. A new access road is also going in the backlands. The paper said the new lines will replace lines along the railway embankment.
The Department of Public Information said more work lies ahead beyond Good Hope. It said electricity lines along the Good Hope-to-Mahaica section still have to be moved. That would take several more months, it said.
The story was first reported by the Department of Public Information.